SONG DA 9 JOIN STOCK COMPANY

XEKAMAN 1 HYDROPOWER PLANT

XEKAMAN 1 HYDROPOWER PLANT

General information

Xekaman 1 Hydropower Plant is constructed on XeKaman river, Sanxay district, Attapeu province, Lao PDR. Xekaman 1 Hydropower Plant has a total capacity of 322 MW, including two levels: upper level is Xekaman 1 Hydropower Plant and lower lever is Xekaman Sanxay Hydropower Plant.

  • Project: Xekaman 1 Hydropower Project
  • Total capacity: 322 MW
  • Location: Sanxai district, Attapeu province, Lao PDR
  • Employer: Viet-Lao Power Joint Stock Company - Song Da Corporation.
  • Main contractor: Song Da Corporation
  • Construction period: 2011 – 2016
  • Commencement in March 2011.

Scope of works performed by Song Da 9

Total quantity performed by Song Da 9:

  • Excavation: 3,648,510 m3
  • Back filling: 188,600 m3
  • RCC: 885,130 m3
  • CVC: 224,370 m3

Including:

  1. RCC:
  • Left bank rolling weir
  • Right bank rolling weir
  • Spillway
  1. Overburden stripping in No.3 Quarry: Excavation and transportation

 

Other project

TUYEN QUANG HYDROPOWER PLANT

Na Hang, Chiem Hoa, Tuyen Quang province

TAN THUONG HYDROPOWER PLANT

Di Linh and Lam Ha district, Lam Dong province

NAM THEUN 1 HYDROPOWER PLANT

Bolikhamxay province, Lao's People Democratic Republic

NAM NGIEP 1 HYDROPOWER PLANT

Bolikhamxay province, Lao's People Democratic Republic

XEKAMAN 3 HYDROPOWER PLANT

Sekong district, Lao's People Democratic Republic 

YALY HYDROPOWER PLANT

Sa Thay - Kon Tum

LAI CHAU HYDROPOWER PLANT

Muong Te - Lai Chau

SON LA HYDROPOWER PLANT

Muong La - Son La