SONG DA 9 JOIN STOCK COMPANY

LAI CHAU HYDROPOWER PLANT

LAI CHAU HYDROPOWER PLANT

General information

Lai Chau Hydropower Plant is a national key project, constructed on the highest level of Da river main stream, the upper level of Son La Hydropower Plant. The construction is commenced on January 5th 2011, generated electricity of three units in November 2016, inaugurated in December 2016 which is 1 year earlier than the National Assembly’s target. Lai Chau Hydropower Plant has a total installed capacity of 1,200 MW, the average annual generation is 4,670.8 million kWh.

  • Project: Lai Chau Hydropower Project
  • Location: Nam Hang Commune, Muong Te District, Lai Chau Province, Vietnam
  • Client: Vietnam Electricity (EVN).
  • Main contractor: Song Da Corporation
  • Construction period: 2010 - 2016

Scope of works performed by Song Da 9

Scope of works performed by Song Da 9
Total quantity performed by Song Da 9:

  • Excavation: 4,283,360 m3
  • Back filling: 1,915,170 m3
  • Overburden stripping, mining and transportation: 8,800,000 m3
  • CC: 1,900,000 m3

Including:

  1. Construction of major works:
  • Earthwork: Excavation and transportation for right bank fixed dam foundation;
  • Earthwork: Excavation and transportation for foundation of flood discharge works and eroded hole;  
  • Earthwork: Excavation and transportation for powerhouse foundation;
  • Earthwork: Excavation and transportation for left bank fixed dam foundation and left bank power waterway (from sectional plane DIII-:-DIII+340, from elevation 265 downward);
  • RCC works.
  1. Construction of diversion works:
  • Earthwork: Excavation, back filling and transportation for diversion works foundation, from sectional plane DIII-:-DIII-380;
  • Back filling and take down upstream cofferdam stage 1; upstream cofferdam stage 2 and half of quantity of downstream cofferdam stage 2; cofferdam stage 3 and stage 4.

 

  1. Construction of auxiliary works:
  • Ground grading for auxiliary works: left bank workshop and parking area; water and electricity supply and specialized hydraulic works;
  • Auxiliary works: left bank workshop and parking area; water and electricity supply and specialized hydraulic works;
  • Site office and camp for Party B; site office for Board of Management of main contractor.
  • Transportation system: NP2 road; NP8 road; NT11 road; part of NT8 road;
  •  Part of technical and domestic water supply system: ground grading for technical water tank.
  1. No.1B quarry:
  • Excavation and transportation of overburden stripping of No.1B quarry, total quantity of 1.9 million m3;
  • Rock transport from No.1B quarry to crushing plants;
  • Drain ditch, install and reinforce rock gabion in construction area.

Other project

TUYEN QUANG HYDROPOWER PLANT

Na Hang, Chiem Hoa, Tuyen Quang province

TAN THUONG HYDROPOWER PLANT

Di Linh and Lam Ha district, Lam Dong province

NAM THEUN 1 HYDROPOWER PLANT

Bolikhamxay province, Lao's People Democratic Republic

NAM NGIEP 1 HYDROPOWER PLANT

Bolikhamxay province, Lao's People Democratic Republic

XEKAMAN 1 HYDROPOWER PLANT

Attapeu province, Lao's People Democratic Republic

XEKAMAN 3 HYDROPOWER PLANT

Sekong district, Lao's People Democratic Republic 

YALY HYDROPOWER PLANT

Sa Thay - Kon Tum

SON LA HYDROPOWER PLANT

Muong La - Son La