Song Da 9 JSC., organized a ceremony to launch the “87-full day emulative Campaign for a successful impoundment target”

Song Da 9 JSC., organized a ceremony to launch the “87-full day emulative Campaign for a successful impoundment target”

In order to accomplish the impoundment target in Pake Hydropower Project in January, 2017 and contribute to the production plan completion in 2016, on date 24th October 2016, in Pake hydropower construction site, the Unions and the Youth Union of Song Da  has together coordinated and held a ceremony to launch the“87-full day emulative Campaign for a successful impoundment target” and  appended  the insignia of  Youth union to the trucks, machines and equipments  in Pake site. Campaign implementation period from the date 20th October 2016 -: - 15th January  2017.

Attending the launching ceremony has Mr. Le Van Hung - Deputy Secretary of the Party Committee and Chairman of Trade Union, and head of emulation campaign; Mr. Nguyen Duc Tho - Deputy General Director of the Company; and all leaders as Secretary of Youth Union of the Company, Pake Hydropower Project Management Board, construction companies, Consultants, Engineers  and all the staff and workers in  construction site Representatives of the construction companies signed the agreement with the emulative determination with successful completion of the campaign objectives in January 2017, this is a very important milestone to ensure the implementation of project schedule. Mr. Tran Dai Nghia - Director of Song Da 9.10 Branch, representatives of the construction companies, Mr. Le Van Anh represents for the younger generation on the site spoke expressed their determination to complete the main objectives are as follows:

No.

Description

Completion date

1

Excavation of right bank foundation pit,  diversion culvert foundation pit to the design elevation +218.5 

15/11/2016

2

Embanking the longitudinal cofferdam  for construction of diversion culvert

30/10/2016

3

Concrete the diversion culvert  from date 15th Nov. 2016

30/12/2016

4

Drilling and Grouting, complete the installation of diversion culvert

valve

5/01/2017

5

Embanking the upstream and downstream cofferdams for river impoundment  

15/01/2017

6

Treated completely and finish the operation roads VH1, VH2

30/11/2016

7

Grout drilling of dam slope of right and left banks and power house

30/12/2016

8

Manage the project ensuring the schedule, quality, safety and saving.

During the campaign

9

Release the Payments promptly as per the Schedule

During the campaign

10

Llaunching the appendment  of insignia of  Youth union to the trucks, machines and equipments  in site

During the campaign

Recognizing the importance of the campaign, with the tradition of labor hero Company in the innovation period and determination to overcome difficulties to complete the task of labor collectives, SD9 makes sure that the campaign will win. Glory will be to those who in time!